An engine lathe costing rs.10000 can produce components at the rate of 6 pieces per hour, another automatic lathe costing rs. 20000 can produce 20 pieces per hour . the operator on either of the machine is to be paid at the rate of rs. 1.50 per hour. Determine the minimum number of pieces which will charge the situation in favour of the automatic lathe